Wednesday, July 8, 2015

Asset Management Improvement Project Part 1

Few days ago, my co-worker telling me that our Director assign him to improving ways of work in branch's logistic and warehouse. Actually, the scope of this assignment is in my area, everything that related to workflow process in branch always comes from my department, the Field Operation & Standardization (FOS) department. So, the assignment transferred to me provided with general requirement. The request is very simple, just make the branch's warehousing area more comfortable to manage, because our customer's asset is there.

Before I tell you more how to plan and achieve this assignment, I'll give you brief explanation about what we means by asset and what is the problem there that makes we need to improve ways of work in branch logistic area. The asset itself is a EDCs, a transactional draft capturing machine. This machine works with magnetic tape that we called credit or debit card issued by bank. Merchants that using EDC just set the nominal purchase by customer in that machine, then inserting customer's credit or debit card, and voila! Customer bank account will be debited as much as nominal of purchasing that has been set by merchant (as much as the good's price, of course)

If our customer (bank, of course) giving EDC Installation order to us, they will send an EDC and its Job Order (contains information where the machine will be installed, due date, etc.) The EDC must stay at our logistic area first, and then will be issued a day before installation’s due date to the merchant. As well as EDC Withdrawal order, the bank just issued Withdrawal Job Order to us, and our technician will go to the merchant as Job Order stated, to take the EDCs from merchant and cutting off connectivity.
EDC Machine

In field operation, installation or withdrawal activity isn't simple as stated above. In our SOP, installation or withdrawal only can be done if merchant’s condition fulfill our SOP Terms and Condition (TC). The terms of installation job is like active phone line, merchant’s name and address is valid (same precisely with jobs order issued by Bank), etc. If Terms and Condition not apply by merchant, our engineer just set job status to pending. The machine will stay at branch’s logistic until job order is re-assigned. The problem arise when the TC-not-comply trend is growing up, logistic area become full with EDC and we need to sort EDC by its age. The old one MUST be forward to Bank’s Logistic because the follow-up respond is timed up. And we don’t have responsibility to manage it anymore.

After we know what kind of machine that we will manage and what the problems there, I set a team of two from my subordinate. Experiencing in leading team, I focused on what kind of personality that can handle this type of project. The team lead for this project assigned to Mr. Budi, he is a senior employee that formerly coordinating area in Jakarta area. The reason is simply, he has high respect from all field operational member in Jakarta that can be used to ease our project implemented in each branch. Besides that, Mr. Budi is compliance person and always obeying any standard that had been agreed by management. He experienced handling resistance issues that always rise when new ways of work being piloting (a thing that I MUST still learn more to him). Mr. Budi will assist by Dendy, a newly hired employee in my team. There are some reason I involve Dendy in this project, he have good logical-brain (A must HAVE ability in team that I recruit, especially when I directing a workflow process for each project), He also well-know about this asset much, because I assign him in other project as a supporting staff that handling branch office’s EDC database and its sub process. So, the composition for the team is: Mr. Budi as instructor and lead our member in branch, and Dendy as conceptor that must well-detail-explained why this improvement must be held in office's branch across Indonesia to each branch leader.

After we set the team to hold this project, we're going to create goal and its mission statement. My role here is to directing the Team to our goals and creating project concepts to meet the goals. The main goal of this project (as I state above) is to manage customer asset easily in Branch's Logistic Area. I break the goal into some mission statement that must be accomplished by me and my Team.
Usually, I try to make the mission statement with what-I-called Milestone Table. Milestone table contains: what will we do? When we do it? Who will do it? (I mean, who's have higher responsibility to doing it well), and when you show it off?

For this project, I invited my teams to attend kickoff and brainstorming meeting. Brainstorming meeting is very very very required. You can share our goal there, share your concept and let others to giving opinion and feedback, discuss and comparing the old ways and the new ways, (with each pros and cons table), at the end, you'll find better solution and its alternatives. At next paragraph I will tell you much about how my team accomplish the goals.

Comparation Old Concept and New Concept (Brainstorming Meeting, Omega Room, June 8 2015)

I'll tell you a little about our previous Branch's Asset Management. This previous project is one of my standardization improvement about 2 years ago. At that time, everything not so crowded like now, so our approach to handle that machine will be slightly different from now on. Want to know interesting thing about this change? Please wait for my second post J